No clarity on funds to complete Golf Avenue, say CHD homebuyers – ET RealEstate

GURUGRAM: The homebuyers of CHD 106, Golf Avenue in Sector 106 are unsure about the funds required for the completion of the project after the Haryana Real Estate Regulatory Authority (HRera) ordered a forensic audit of the accounts of the developer and floated the possibility of takeover by the buyers.

In a recent order, HRera ordered for a forensic audit by Currie & Brown, an international consultancy firm, which will submit cash inflow and outflow of the project from beginning till now, as well as the cost estimates for its completion.

The regulatory authority also directed that the auditor submit a mitigation plan for completion of the project. The builder couldn’t be reached for a comment.

While a few homebuyers said once allottees take over, four towers will be completed for handover within six months, other said the lack of funds would be the main hurdle in project completion.

CHD Developers had launched a housing project under Empire Realtech in 2011 — 106, Golf Avenue in Sector 106 — with a promise to offer possession by December 2016. The homes have, however, not been delivered yet. The promoter intimated the revised date for completion to HRera as June 30, 2021 at the time of registration in 2016.

On the call of the developer, a meeting was held with six representatives of the buyers’ group, where they insisted that the developer deposit Rs 5 crore in an escrow account. The developer expressed his inability to deposit cash and in lieu agreed to transfer six unsold flats to the association.

Vishal Rekhi, a homebuyer, said: “The main issue with our stalled project is funds. There is nothing in the order suggesting infusion of funds. There is a requirement of at least Rs 35 crore, which has to be given by the builder. As an authority, Rera lacks teeth to force the builder to infuse funds.”

Jitender Pal, another homebuyer, added: “The developer has already collected over Rs 500 crore from homebuyers. At least 70% of this amount had to be kept in a separate escrow account and should have been used only for construction, which is not the case here.”

He said if the developer had followed the norms, the project would have been completed as cost of construction was just Rs 190 crore.

Savishesh Raj, who also bought a flat in the project, said the developer has claimed it will hand over around half a dozen units of unsold inventory in lieu of funds, but people are unlikely to invest in a stalled project. “We need liquid funds, but the HRera order mentions nothing on the matter. Only the National Company Law Tribunal can help the aggrieved homebuyers. We will pursue the case in the tribunal,” Raj said.



Source link

Gurugram: DTCP directs ILD to submit plan to wrap up delayed projects – ET RealEstate

GURUGRAM: Taking serious note of residential projects in the city which have been delayed for over three years, the department of town and country planning has directed the builder, International Land Developers (ILD), to prepare and submit an action plan for their completion within a week.

District town planner (DTP) RS Batth said if ILD fails to submit the plan within the stipulated time, the department would recommend the registration of an FIR against the developer.

The move comes after homebuyers of ILD Arete (Sector 33) and ILD Greens (Sector 37C) met the DTP on Tuesday over three years’ delay in completion and lack of amenities in the projects. They are now planning to file a complaint with H-Rera against the builder.

The developer told TOI that a meeting was held by the DTP for resumption of work at ILD Arete. “Company representatives are in regular touch with the clients and have shared updates with them,” an ILD official said.

Launched in 2013, Arete is only 60% complete. The developer had promised possession of the project, which is spread over 11 acres and has 550 units in eight towers, in December 2019. “ILD’s licence has expired and the developer got registered with H-Rera only this month. They are talking of delivery in 2022, but it doesn’t seem likely even by then,” said Sunil Sharma, a buyer.

Vipin Kumar, who bought a flat in ILD Greens — which has six towers — said the builder offered possession in October 2016, eight years after booking. “Almost four years later, half of the towers are incomplete. Residents still don’t have permanent electricity, water and sewer connections,” he said.

Batth directed the builder to immediately apply for electricity and water connections, comply with lift and fire safety norms and complete the formalities to hand over basic amenities to the RWA. Batth has also directed his team to inspect both the project sites and check construction status. “A notice was served to the directors of ILD to attend the meeting scheduled on Tuesday, but they didn’t turn up,” he said.



Source link

Gurugram: Three committees to resolve issues of CHD Developers, Ramprastha Group projects – ET RealEstate

GURUGRAM: Around 250 buyers of around 90 residential projects in Gurgaon attended the first ‘Justice for homebuyers’ meet organised by Badshapur MLA Rakesh Daultabad at John Hall in Civil Lines. Apart from the MLA, officials from the district administration, department of town and country planning (DTCP), H-Rera, Municipal Corporation of Gurgaon and police were also present.

Daultabad directed officials to form three special committees in consultation with DTCP and H-Rera for speedy resolution of matters relating to projects under two private builders — CHD Developers Ltd and Ramprastha Group — as well as those under HSIIDC in Manesar.

A senior DTCP official said most of the complaints centred on high maintenance charges in affordable houses, poor construction quality and demands for structural audit of projects, absence of roads, pending occupation certificates and lack of amenities.

Meanwhile, buyers attending the meeting complained of lack of adherence to social distancing norms and “chaos”; many returned disappointed as they didn’t get an opportunity to share their problems with officials.

“The biggest concern was that no social distancing norms were followed at the meeting. Also, sanitisers were kept there, but no thermal scanning was done,” said Vishal Rekhi, a resident of CHD Avenue 71.

Another participant, Anurag Upadhyay from Ramprastha Skyz society, said such meetings will help buyers only if officials are able to provide solutions to their issues.

A DTCP official said strict action will be taken on all the complaints within 30 days, including filing of FIRs against the defaulting builders.

“Most departments are aware of the issues raised in the meeting. Working on solutions would be better, rather than discussing the problems again and again,” another official said.

Asked about the deadline to resolve the issues discussed in the meeting, MLA Rakesh Daultabad said they are of different natures. “Some can be resolved in one month, while others may take a few months. We will hold the meet regularly and deadlines will be fixed for the issues separately,” he said.



Source link